Synmphony Park Bridge
Vehicle Access Bridge from one parking garage over 3 railroad tracks (Main lines between Denver and Los Angeles)
PROJECT DESCRIPTION



OVERVIEW
Main Span 135’-0, Secondary Span 35’-0, both bridges fit with precision. Side Trusses shop fabricated as 1 piece and shipped to site as 1 piece on specialty trailer.
CHALLENGES OVERCOME
Bridge had to be fully erected and lifted over the parking garage at night in a 3-hour window due to the railroad could not be shut down any longer than that.
JST Beach Pavilion
PROJECT DESCRIPTION
93-tons of structural steel with cruciform columns.
ITEMS SUPPLIED
Structural steel, and Verco deck.
SURFACE COATING
Shop Primer
CHALLENGES OVERCOME
Cruciform column with extremely restricted welding access, requiring pre-coating the sub-assemblies before welding.



DOWNTOWN STADIUM
PROJECT DESCRIPTION
A 5,000 seat, open-air, stadium for Spokane Public Schools. Consisting of concrete footings and walls, masonry, metal framed walls, steel columns, steel beams and steel roof framing, totaling 427 tons of steel elements.


ITEMS SUPPLIED
structural steel and miscellaneous steel (including delegated design of stairs, guardrails, and handrails).
SURFACE COATING
Galvanizing, shop primer, powder-coating, and epoxy coating
CHALLENGES OVERCOME
Coordinated with multiple trades through BIM, email, virtual & in-person meetings ensuring successful integration of scope items, and navigated complications when tolerance accumulations between parties hindered installation.

RENTON ES #16
PROJECT DESCRIPTION
Over 81 thousand square ft School. Structural Steel framing with integrated Cross Laminated Timber members, and delegated design of steel & timber stairs and railing systems throughout the school.
ITEMS SUPPLIED
Structural steel, and Verco deck.
SURFACE COATING
Shop Primer
CHALLENGES OVERCOME
Cruciform column with extremely restricted welding access, requiring pre-coating the sub-assemblies before welding.